Oracle Invokes Force Majeure on $18B AI Data Center
Oracle has invoked a force majeure clause to shield itself from financial obligations on Project Jupiter, an $18 billion AI data center in New Mexico slated to serve OpenAI under the Stargate initiative. The construction is halted by environmental lawsuits, energy supply issues, and local protests. Oracle and developer Blue Owl reassure that commitments remain, but banks like Santander, Jefferies, and BNP Paribas are seeking to offload the loans at a discount on secondary markets. Analysts warn that only 35% of planned AI infrastructure projects will materialize due to energy and funding gaps. Morgan Stanley estimates $2.9 trillion in global data center investment needed by 2028, with hidden debts among big tech reaching $1.65 trillion, Oracle owing over $270 billion.
- •Oracle invoked force majeure on Project Jupiter, an $18 billion AI data center in New Mexico.
- •The data center is part of the Stargate initiative and will serve OpenAI.
- •Construction is currently blocked by environmental lawsuits, energy supply issues, and local protests.